January 22, 2008: Vancouver, British Columbia – MPAC Industries Corp. (the “Company” or “MPAC”) is pleased to advise its shareholders and the investment community of the following activities concerning the Soma coal refining plant (the “Plant”) on the leased site (the “Leased Site”) located in the western region of Turkey close to the City of Izmir (the third largest Turkish city).

As discussed in the Company’s News Release of December 6, 2007, one Company Executive and the Contractor (“Canadian Contractor”) left for Turkey on December 26, 2007. That Executive has since returned to Canada after attending the Leased Site, meeting with members of the business community, and reviewing other coal deposits. The Contractor remained in Turkey to address the Plant start-up process. The Contractor has been engaged under contract with MPAC for a period of six (6) months with an option to extend the agreement upon mutually agreed upon terms. Incidentally, this particular Contractor has over twenty-five (25) years of experience in various mining and mineral processing plants around the world.

The loading and storage areas for the raw and refined coal have been inspected; the crushing and conveyor circuits have been tested and interlocked; the initial number of tailings and concentrate ponds have been constructed; the commissioning of the coal refining technology has now been completed; and the first test quantities of run-of-mine coal (“ROM Coal”) have been processed through the Plant.

The ROM Coal was not introduced into the system until the required parameters had been set by the Contractor and had been fully tested. In addition, in order to test the efficiency of the Plant to its maximum level, the Company requested that the Mine Owner supply coal from a seam with a higher ash content. The ROM test Coal, with twenty-six hundred (2,600) kilocalories and an ash content of forty percent (40%) was then introduced into the Plant. A number of samples of the resulting refined coal (“Refined Coal”) have now been sent to a laboratory in Turkey. The Company expects the certified results of these tests within the next few days.


However, from the initial results that are being communicated to the Company as of today, it is apparent that the Plant is operating according to MPAC’s expectations. These preliminary results indicate that the calorific value was increased from twenty-six hundred (2,600) to forty-eight hundred (4,800), an
increase of about forty five percent (45%). Ash and sulphur content reductions will be reported once the final test results are known.

Meanwhile, a number of ancillary equipment and Plant performance issues were identified during the commissioning and testing phase. These issues will be addressed in the next few weeks. Once completed, these adjustments will allow the Plant to be prepared for commercial production. The Turkish contractors are expected to be at the Plant later in the week to fine-tune their portion of the Plant to harmonize with the properties of the input commodity. For the balance of the current month, the Plant could undergo further test runs and process further quantities of coal.

The resulting Refined Coal, after the test results have been certified, will be delivered to the Mine Owner, and the Company will be credited with this delivery in accordance with the Coal Refining Agreement. All of the coal processed at the Plant will be treated in the same manner.

Barring any unforeseen circumstances, MPAC is forecasting its February 2008 Refined Coal production at 25,000 tonnes. Production target figures for March and April 2008 will be announced at a later date based upon the performance of the Plant in February.

With the results obtained to date from the Plant, MPAC is not in a position to comment on the coal input / output ratios (tonnage and efficiency). Once the Plant has processed sufficient quantities of ROM Coal, the Company will be in a better position to analyze the data and make further comment.

The Company is proceeding with the construction of additional concentrate and tailings ponds on the Leased Site in order to prepare for the forecast annual production of a minimum of 400,000 tonnes of Refined Coal from the Leased Site.

Fortuitously, the property immediately adjacent to the Leased Site recently became available and MPAC has entered into a lease with the owner to convert that second leased property into a storage area for the Refined Coal produced. As this second adjacent property has leasehold improvements already, including a roof to shelter the finished product from the elements, the Company has capitalized early on this future expansion opportunity.

The Company recognizes that it has tested the patience of the investors in the time it has taken in arriving at this stage in its development. However, there are extenuating circumstances that should be considered: working in a new country that has a very different set of business practices and procedures; delays caused by a four-day religious holiday in Turkey; the Christmas and New Years holidays; inclement weather; and the limited local availability of specialized equipment necessary to complete the Plant circuit. Despite the delays to date, the Company is very satisfied with the achievement of commissioning the various components of the Plant circuit and the initial testing of the completed integrated circuit.

The Company continues to look forward to positive returns from this project according to the projections contained in the Business Plan.

This news release contains forward-looking statements, which are based on MPAC
Industries’ current internal expectations, estimates, projections, assumptions and
beliefs, which may prove to be incorrect. The forward-looking statements are not
guarantees of future performances and undue reliance should not be placed on
them. Actual results may differ materially as a result of any number of factors and
uncertainties, many of which factors are beyond the Company’s control. MPAC
Industries Corporation undertakes no obligation to revise any forward-looking

BY THE ORDER OF THE BOARD
________________________________
Firoz Lakhani
President & CEO

The TSX Venture Exchange neither approved nor disapproved the contents of this news release.
The TSX Venture Exchange does not accept responsibility for the adequacy or accuracy of this
news release.

 

 


Untitled Document

News Releases

• June25, 2008
MPAC is pleased to provide its shareholders and the investment community with an update concerning the election of the new Board of Directors...
(Read More...)
• June23, 2008
MPAC wishes to advise its shareholders and the investment community that the Exchange has granted a forty-five (45) day extension...
(Read More...)
• June23, 2008
MPAC announces that, under it’s stock option plan, it has granted incentive stock options to directors, officers, and/or consultants...
(Read More...)
• May 6, 2008
MPAC is pleased to provide its shareholders and the investment community an update regarding the coal refining pilot plant (the “Plant”) located in the City of Soma in Turkey.
(Read More...)
• April 4, 2008
MPAC is pleased to provide its shareholders and the investment community an update regarding the Soma coal refining Pilot Plant...
(Read More...)
• March 31, 2008
MPAC announces that, under it’s stock option plan, it has granted incentive stock options to directors, officers, and/or consultants of the Company...
(Read More...)
• March 11, 2008
MPAC is pleased to announce the commencement of limited commercial production at the coal refining plant (the “Plant”) located on the leased site (the “Leased Site”) in Soma, Turkey.
(Read More...)
• February 18, 2008
MPAC announces that, further to its News Release of January 28, 2008, the Company, has closed its Non-Brokered Private Placement (the “Placement”) comprised of 1,815,000 units with twenty (20) placees at a price of $0.13 per unit.
(Read More...)
• February 14, 2008
MPAC is pleased to provide its shareholders and the investment community of the following up-date concerning the Soma coal refining plant (the “Plant”) on the leased site (the “Leased Site”) located in the City of Soma in the western part of Turkey.
(Read More...)
• January 29, 2008
MPAC is pleased to release the results of two (2) of the test samples from the coal refining plant (the “Plant”) located on the leased site (the “Leased Site”) in Soma, Turkey. Further results from subsequent tests will be released as they become available.
(Read More...)
• January 28, 2008
MPAC is pleased to announce that it has concluded negotiations for a non-brokered private placement of a maximum of 1,500,000 units (the “Offering”) at a price of $0.13 (thirteen cents) per unit.
(Read More...)
• January 22, 2008
MPAC is pleased to advise its shareholders and the investment community of the following activities concerning the Soma coal refining plant (Read More...)
• December 6, 2007
MPAC is pleased to advise its shareholders and the investment community of the following activities concerning the Soma leased site (the “Leased Site”).
(Read more...)
• November 9, 2007
MPAC announces that, further to its News Releases of October 30, 2007 and November 6, 2007, the Company, pursuant to the Conditional Acceptance from the Exchange, has closed its Non-Brokered Private Placement (the “Placement”) comprised of 1,260,000 units with twelve (12) placees at a price of $0.14 per unit.
(Read More...)
• November 6, 2007
MPAC announces that, further to its News Release of October 30, 2007, the Company has increased the maximum offering of its Non-Brokered Private Placement from $154,000 (1,100,000 units) to $180,600 (1,290,000 units).
(Read More...)
• November 5, 2007
MPAC is pleased to advise its shareholders and the investment community of the following activities concerning the Soma coal mine...
(Read More...)
• October 30, 2007
MPAC is pleased to announce that it has concluded negotiations for a non-brokered private placement of a maximum of 1,100,000 units (the “Offering”) at a price of $0.14 (fourteen cents) per unit.
(Read More...)
• October 24, 2007

MPAC has now entered into a binding lease agreement for the leased site in Soma as referred to in its News Release of October 22, 2007.
(Read More...)

• October 22, 2007
MPAC is pleased to advise its shareholders and the investment community of the following activities concerning the Soma coal mine...
(Read More...)
• September 17, 2007
MPAC Is pleased to advise its shareholders and the investment community of the following activities concerning the Soma coal mine.
(Read More...)
• August 30, 2007
MPAC announces that, under it’s stock option plan, it has granted incentive stock options..
(Read More...)
• August 21, 2007
MPAC is pleased to announce that, in keeping with its intent to initially concentrate its efforts to refine coal in the western part of Turkey, it has entered into a Memorandum of Understanding (the “MOU”) with the Yalvaç coal mine owner to refine their coal using the Company’s coal upgrading and refining
process.
(Read More...)
• August 4, 2007
MPAC announces that, further to its News Release of July 9, 2007, the Company has closed its Non-Brokered Private Placement comprised of 1,510,000 units with twenty-three (23) Placees at a price of $0.17 per unit.
(Read More...)
• July 30, 2007
MPAC is pleased to announce that it has secured the required promissory note (the “Note”) from E.E. Madencilik Dagitim Sanay Ticareti ve Pazarlama Ltd. Sti (“E&E”) in accordance with the terms of the recently announced definitive agreement (the “Agreement”) with E&E.
(Read More...)
• July 17, 2007
MPAC is pleased to announce that it has entered into a definitive agreement (the “Definitive Agreement”) with E.E.
(Read More..)
• July 9, 2007
MPAC is pleased to announce that it has re-priced its recently announced non-brokered private placement and adjusted the maximum number of units available for offer.
(Read More...)
• July 3, 2007

MPAC is pleased to announce that the Company has entered into a binding Memorandum of Understanding (the “MOU”) with the Soma coal mine owner to refine their coal using the Company’s coal upgrading and refining process.
(Read More...)

• June 20, 2007
MPAC is pleased to announce that the final testing of the coal refining pilot plant equipment (the “Equipment”) has been completed by the engineering staff from Turkey.
(Read More...)
• June 1, 2007
MPAC announces that, under it’s stock option plan, it has granted incentive stock options...
(Read More...)
• May 31, 2007
MPAC has filed its annual audited financial statements and management's discussion and analysis...
(Read More...)
• May 22, 2007
MPAC intends to implement accelerated exercise provisions on warrants issued in its November 30, 2006 non-brokered Private Placement...
(Read More...)
• May 11, 2007
MPAC announces that it has revised the scheduling of the planned testing of the Coal Refining Plant...
(Read More...)
• May 1, 2007
MPAC reports that it has been delayed in filing its Annual Audited Financial Statements and Annual Management Discussion & Analysis...
(Read More...)
• April 25, 2007
MPAC wishes to provide the following update to its activities in Turkey since the last News Release of March 26, 2007.
(Read More...)
• March 26, 2007
MPAC is pleased to advise that it has closed the previously announced Non-Brokered Private Placement...
(Read More...)
• March 5, 2007
MPAC is pleased to provide the following update to its activities in Turkey.
(Read More...)
• February 7, 2007
MPAC is pleased to provide the following update to its activities in Turkey.
(Read More...)
• January 4, 2007
MPAC is pleased to announce that the major components of the coal refining plant (the “Plant”) have arrived in Tokat / Zile and have been substantially installed.
(Read More...)
• December 7, 2006
MPAC signs additional MOUs
(Read More...)
• December 1, 2006
MPAC Industries grants stock options.
(Read More...)
• November 30, 2006
MPAC Industries close $75,000 private placement offering.
(Read More...)
• November 23, 2006
MPAC arranges up to a maximum of
$60,000 financing.
(Read More...)
• November 20, 2006
MPAC Industries Corp. is pleased to announce that the plant equipment has safely arrived at the port of Istanbul.
(Read More...)
• October 25, 2006
MPAC Industries Corp. is pleased to provide the following corporate update on its recent activities.
(Read More...)
• October 13, 2006
MPAC Industries Corp. Closes $405,000 Private Placement Offering.
(Read More...)
• October 13, 2006
MPAC grants stock options.
(Read More...)
• September 28, 2006
MPAC directors & officers exercise stock options.
(Read More...)
• September 21, 2006
MPAC is pleased to announce that it has entered into a definitive agreement (the Definitive Agreement”) with ALCE Cevre Teknigi Ltd.
(Read More...)
• September 13, 2006
MPAC is pleased to announce that the testing of the equipment that has beenmanufactured for MPAC has now been successfully concluded at the manufacturer’s plant.
(Read More...)
• August 28, 2006
MPAC is pleased to announce that it has concluded negations for a private placement of a maximum of 4,000,000 units...
(Read more...)
• August 23, 2006
MPAC is pleased to announce that it has completed its preliminary due diligence on the Tokat/Zile coal mine...
(Read More...)
• June 29, 2006
MPAC Industries Corp. announces that, under it’s stock option plan...
(Read More...)
• April 20, 2006
MPAC is pleased to provide the following corporate update of its activities...
(Read More...)
• January 11, 2006
MPAC is pleased to provide the following corporate update of its activities...
(Read More...)
• December 19, 2005
MPAC announces that, under its stock option plan, it has granted incentive stock options to directors...
(Read More...)
• November 21, 2005
Pursuant to the shareholder approval at the Company’s Annual General Meeting held on June 24, 2004, the Company has now issued a total of 500,000 ...
(Read More...)
• November 15 , 2005
MPAC is pleased to announce the closing of its private placement of 6,004,000 Units at $0.11 per Unit...
(Read More...)
• October 4, 2005
MPAC Industries Corp. (the “Company or “MPAC”) is pleased to announce that its shares will be reinstated for trading on NEX on October 5, 2005...
(Read more...)
• July 20, 2005
MPAC Industries Corporation (the "Company" or “MPAC”) is pleased to announce that First Associates Investments Inc. (“FAI”) of Calgary, Alberta has, subject to completion of satisfactory due diligence...
(Read more...)
• December 9, 2004
MPAC Industries Corp. (the “Company”
or “MPAC”) has signed a Heads of Agreement under a binding Memorandum of Understanding (the “MOU”) with Simsek Grubu...
(Read more...)

News Release Archive

Read More News...

Stock Prices

TSX- Venture: MPN
CAN: $0.08    Change: 0.00

Prices delayed up to 20 minutes
 


 

Site Developed and Maintained by Media Button.com Copyright 2005 All rights reserved.